详细信息
安装要求Installation requirements
1、过滤机必须装在泵的出水口,在过滤机的出水口必须安装止回阀,防止突然停水时产生瞬间背压造成滤网损坏。
2、设备安装的管网应保证压力稳定,且在设备设计的压力范围内。
3、设备应保持水平安装,排污口不得上扬(如需上扬,需增加排污泵),安装时要尽量少弯头,确保排水畅通。
4、过滤机进出水口之间应设置旁通阀,以备系统故障或检修时使用。
5、设备进出水管路上需设置压力表,便于观测系统运行压力及压力损失。
6、设备出水管路上应设置取样放空阀,便于调试时滤后水取样以及长期停机保存前的设备放空。
7、设备安装时四周应预留出1米检修空间。
①The filter must be installed in the pump outlet. The reflux valve must be installed in the filter's inlet & outlet in order to avoid the filtration screen breakage caused by instant negative pressure and back pressure when stops water supply suddenly.
②The pipe network equipment installation shall ensure that the pressure is stable. And the pressure in the device is in the design value range.
③Equipment should be keeping in the horizontal installation. And the sewage outlet shall not be up(If need to rise, need to increase sewage pumps ). Please turn no corners as less as you can to ensure the smooth drainage when install the filter.
④ Install the bypass valve between the inlet and outlet to prepare for the system trouble shooting or maintenance.
⑤On the pipe line of the outlet, you should set the pressure gauge to observe the working pressure of the system and the pressure loss.
⑥On the outlet pipe should be set sampling release valve for water sampling after filtering and long-term shutdown of equipment to save pre-venting.
⑦1m overhaul space should be reserved around the installation of equipm